What an availability payment is and what it buys
In an availability-payment concession a government pays a private partner a fixed sum for keeping an asset open and working, whether or not anybody uses it. By the end you will know who carries demand risk, what the payment covers in the decades after construction ends, and the one clause that gives the public any leverage.
Prepared by
Last reviewed Published 3 minute read
插图:The Cefa Brief
In an availability-payment concession, a private consortium designs a piece of public infrastructure, builds it, raises the money to build it, then operates and maintains it for a fixed term, often twenty-five or thirty years. The public authority pays nothing while it is being built. Once the asset opens, the authority pays a set sum at set intervals for as long as the asset remains available to a standard written into the contract. At the end of the term the asset goes back to the authority.
The word availability is the whole of it. The payment does not rise when traffic is heavy and does not fall when it is light. It falls when a lane is shut, a lift is broken, a platform is unlit or a response time is missed. Users may still pay a toll, but if they do the toll goes to the authority, not to the partner.
Who carries the risk that nobody comes
This is the dividing line between the two families of concession. In a demand-risk deal, usually a toll concession, the private partner collects the revenue from users and lives on it. If the forecast traffic does not arrive, the partner's equity absorbs the loss, and several American toll concessions have gone through bankruptcy on exactly that. In an availability deal the authority keeps demand risk, because the authority is the one paying. What the partner still carries is the risk of building late, building badly, and of the asset breaking down later.
That allocation is chosen, not discovered. Demand risk suits an asset where use can be measured and priced and where a private forecast is worth something. Availability suits an asset where usage is not the point: a courthouse, a school, a water treatment works, a road nobody would accept a toll on.
What the payment covers after the ribbon is cut
The payment is a single line in a budget that covers at least four things at once: repayment of the construction debt, a return to the equity investors, the cost of running the asset day to day, and lifecycle renewal, meaning the planned replacement of the parts that wear out before the term is up. Most of the contract's years are operating years, and most of the work in those years is labour. The chart is a reminder of what that labour costs in one state: not the headline engineering that gets photographed, but the maintenance, the repairs, the cleaning and the moving of things.
Handback is the clause that makes lifecycle renewal real. The contract specifies the condition the asset must be in when it returns to public hands, and inspections in the final years decide whether it is. Without that clause a partner would have every reason to let the asset decay towards the end of the term, spending nothing it will not be around to regret.
Where the disagreement is
Supporters argue that paying only for performance, across decades, buys maintenance that public budgets never protect: a highway agency can defer resurfacing for a decade when the legislature is short, and a concessionaire facing deductions cannot. Critics answer that an availability payment is borrowing by another name, at a private cost of capital above what a government pays, and that it can be arranged so the obligation does not appear as public debt even though a future budget must honour it. Both points can be true at once, which is why the fight is usually about the counterfactual: whether the comparison is against a well-funded public works department or the one that actually exists.
The test to carry into the next announcement is a single question: what has to go wrong before the payment falls? If the answer is that traffic disappoints, this is a demand deal and the private partner is exposed. If the answer is that a lane stayed closed longer than the contract allows, it is an availability deal and the public is exposed to demand but protected on performance. If the answer is that nothing reduces the payment, somebody has sold a bond and called it a partnership.
Each author told us that for this piece they hold no interest a reader would think relevant.
Explainers are written and kept up to date by The Cefa Brief’s editors. An Explainer is background CEFA stands behind. It is not one author’s argument, and it is not a CEFA position on what anyone should do. If something here is wrong or out of date, write to applied@thecefa.org.
© 2024 Center for Economics & Foreign Affairs. To republish it, see our republication terms. Republishing
Share
The Cefa Brief · applied.thecefa.org/cefa-brief/what-an-availability-payment-buys · Printed from the web edition